• MDC – Lio Jetty Project in El Nido, Palawan was awarded to Riofil Corporation last March 2016 and Completed on March 2017.

    April 18, 2016

  • Royal Cargo – North Hub Project in Plaridel, Bulacan was awarded to Riofil Corporation last November 2016. Progress as of April 2018 is 98.93%.

    November 25, 2016

  • YTPI – Phase 3 Restoration Project in Clarkfield, Pamapanga was awarded to Riofil Corporation in 1st Quarter of 2018. Progress as of April 2018 is 9.45%.

    May 10, 2018

  • PHPC – Construction of Generator Building for HGST Project in Laguna Technopark, Binan, Laguna, was awarded to Riofil Corporation last May 2017 and to be Completed in May 2018.

    May 10, 2018

  • PSC – Construction of Foundation for NEW EP in Villanueva, Misamis Oriental was awarded to Riofil Corporation last September 2017 and Completed in April 2018.

    May 10, 2018

  • PSC Installation of Sheet Piles (88pcs) for Cargo Berth Damage Portion (Phase 1) in Villanueva, Misamis Oriental was awarded to Riofil Corporation last May 2017 and Completed in November 2017.

    May 10, 2018

  • PSC – Design of Sinter Building Expansion in Villanueva, Misamis Oriental was awarded to Riofil Corporation last February 2018. Progress as of April 2018 is ____.

    May 10, 2018

  • PMSC – Sizing Plant Yard #2 Expansion (Exclude Culvert) in Garcia, Hernandez, Bohol was awarded to Riofil Corporation last September 2017. Progress as of April 2018 is 69.10%.

    May 10, 2018

  • PMSC – Renewal of Shiploader (Civil Works) in Brgy. Pugalo, Alcoy, Cebu was awarded to Riofil Corporation last November 2017. Progress as of April 2018 is 84.17%.

    May 10, 2018

  • A Food Factory Building Project in Cavite was awarded to Riofil Corporation last September 2015 and Completed on April 2016.

    April 18, 2016

  • Food Factory Expansion Project in Cavite was awarded last October 2013 to Riofil Corporation and completed on October 2015.

    March 1, 2016

  • Design and Construction of a Generator House was also awarded to Riofil in February 2015, and completed on October 2015.

    March 1, 2016

  • Design and Construction of a Building expansion in Laguna Technology Binan, Laguna commenced in February 2015, and completed on June 2015.

    March 1, 2016

  • Construction of Factory Set-up Project in Calamba City, Laguna Technology, Binan, Laguna commenced on February 2015 and completed on April 2015. (HEWTECH)

    March 1, 2016

  • The Management announced that Riofil Corporation has been awarded last March 3, 2015 the Design & Construction of a New Jetty (55,000DWT) in Bohol and was completed last January 2016. (RESTORATION)

    March 1, 2016

  • Design and Construction of Jetty & Trestle Works for Misamis 3X135 Coal-Fired Power Plant Project located in PHIVIDEC Industrial Estate, Villanueva, Misamis Oriental was completed last December 2015. (FDC)

    March 1, 2016

  • A Construction of Food Manufacturing Facility has been awarded last November 2015 . (NESTLE)

    March 1, 2016

  • Effective January 25, 2016, please be informed that our Engineering Office at LTI Gate 3 Barangay Timbao, Biñan, Laguna has moved to RIOFIL Central Office located in Unit 1704-1706 Hanston Square Building, 17 San Miguel Avenue, Ortigas Center, Pasig City, with Tel. No. (02) 633-4053 and Fax No. (02) 477-9902. (OFFICE)

    March 1, 2016

JRE Lofo

D-U-N-S® Number

7 1 - 8 8 0 - 5 5 5 9

ISO