STEAG – Mindanao 210mw Net Coal-Fired Power Plant, Jetty (45,000DWT)

Owner/Client:
- STEAG – State Power, Inc.
Scope of Work:
- Design and construction of Jetty Facilities Project
Location:
- Phividec Industrial Estate, Villanueva Misamis Oriental
Quantities:
- Steel Pipe Piles – 1,815 tons.
- Unloading Jetty – 12000X192000
- Diameter – 900mm, t16/14, SKK400
- Mooring Dolphin Diameter – 900mm, t16/14, SKK400
- Catwalk Pier Diameter – 900mm, t16/14, SKK400
- Conveyor Pier Diameter – 500mm, t9, SKK400
- Conveyor Foundation – Drive PC Piles, 400mmX400mm
- Concrete – 3,000 psi
Duration:
- 532 Calendar Days (February 2004 – July 2005)