Restoration of PMSC Bohol Plant Port Facilities Project – 55,000DWT

Owner/Client:
- Philippine Mining Service Corporation
Scope of Work:
- Construction of One (1) Unit (PF) Platform for Ship-Loader
- Construction of One (1) Unit (MD) Mooring Dolphin
- Construction of Six (6) units (BD) Breasting Dolphins
- Construction of Three (3) Units (TP) Trestle Pier
- Construction of Eleven (11) Units (CP) Catwalk Pier
- Installation of Anchor Bolts for Ship-Loader
- Installation of Eight (8) Units Rubber Fenders
- Installation of Seven (7) Units 100T Bollards
- Installation of Twenty One (21) Spans Catwalk Structures
- Installation of Two (2) Structural Stairs
Location:
- Barangay West Canayoan, Garcia-Hernandez, Bohol, Philippines
Quantities:
- Steel Pipe Piles – 96pcs. and 1,314,847 tons.
- Maximum Diameter – 900mm
- Maximum Thickness – 16/12mm
- Maximum Length – 46m
- Concrete – 1260 cu.m.
Duration:
- March 2015 – January 2016