Yokohama Tire West Plant Project (Phase 1)

Owner/Client:
- Yokohama Tire Philippines, Inc.
Scope of Work:
- Civil and Building-Mechanical Works (EPC Contracts)
- Mixing Building 3-Storey w/ Floor Area of 8,900 sq.m.
- Composed of Main Factory w/ Floor Area of 65,000 sq.m.
- Other Utility Buildings:
- Waste Water Treatment Plant
- Boiler / Compressor Room
- Warehouse
- Locker Room
- Machinery Building
Location:
- IE-5 Clark Special Economic Zone, Clarkfield, Pampanga
Duration:
- October 2011 – February 2013